The main tunnel of the Zojila Tunnel Project achieved breakthrough at its eastern portal at Minamarg (Kargil district) on 9 June 2026, witnessed by Union Minister Nitin Gadkari.
The ~14 km bi-directional tunnel between Baltal and Minamarg on NH-1 costs about ₹6,800 crore and is built at 2,900-3,310 m; it will give year-round road access between Jammu & Kashmir and Ladakh.
It cuts Sonamarg-Minamarg travel from nearly two hours to about 30 minutes; NHIDCL is the executing agency.
The Minister put road and tunnel works between Kargil and Leh at about ₹18,000 crore and highway projects across J&K at about ₹1.35 lakh crore.
Zoji La (3,528 m, 'pass of blizzards') on the Great Himalayan range links the Kashmir Valley with Dras and the Suru Valley and closes for months in winter. The Zojila Tunnel runs beneath it; the 6.5 km Z-Morh (Sonamarg) Tunnel on the same NH-1, opened on 13 January 2025, keeps the Gagangir-Sonamarg stretch open, so together they complete the winter-proof link from Srinagar to Dras. Beyond Kargil, Fotu La (4,108 m) is the highest point on the Srinagar-Leh highway; Tanglang La (~5,328 m) is the highest on the Manali-Leh route, which also crosses Baralacha La and Lachulung La.
CPSU of the Ministry of Road Transport & Highways, incorporated 18 July 2014 under the Companies Act, 2013; builds highways in strategic, border and North-Eastern areas; executing agency for Zojila and operator of the Z-Morh tunnel
Builds the Shinku La Tunnel (4.1 km twin-tube, ~15,800 ft) — set to be the world's highest tunnel, construction launched 26 July 2024; built the Atal Tunnel
| Tunnel | Bypasses / Route | Length | Status |
|---|---|---|---|
| Zojila | Zoji La, NH-1 (Baltal-Minamarg) | ~14 km, single tube | Main tube breakthrough 9 June 2026 |
| Z-Morh (Sonamarg) | Gagangir-Sonamarg, NH-1 | 6.5 km | Opened 13 Jan 2025 |
| Atal (Rohtang) | Rohtang Pass, Manali-Lahaul | 9.02 km | Opened 3 Oct 2020; longest highway tunnel above 10,000 ft |
| Shinku La | Manali-Darcha-Padum axis | 4.1 km, twin tube | Construction began July 2024 |
Also called the sequential excavation method: the tunnel is dug in stages and the surrounding rock is made to carry its own load, supported immediately by rock bolts, wire mesh and sprayed concrete (shotcrete), with continuous monitoring — suited to unstable Himalayan geology.
GS Paper 1 > Geography > Mountain Passes; GS Paper 3 > Infrastructure / Border Area Security
General Awareness > Static GK > Tunnels and Passes of India
3,528 m pass on the Great Himalayan range linking the Kashmir Valley with Dras; crossed by NH-1
MoRTH CPSU (2014) for strategic and border-area highways; executing Zojila
Sequential excavation with rock bolts and shotcrete; the rock carries its own load