The Mumbai-Ahmedabad High-Speed Rail (MAHSR), India's first bullet-train corridor, is 508 km long with 12 stations; the first service is expected in August 2027.
Design speed is 350 kmph and operational speed 320 kmph, cutting Mumbai-Ahmedabad travel to about 1 hour 58 minutes.
India's first undersea rail tunnel (about 7 km under Thane Creek) is part of a 21 km tunnel section; 4.8 km between Ghansoli and Shilphata is complete.
Bridges over 17 of the corridor's 25 rivers are complete; at the Mahi bridge 11 of 12 wells are done.
Union Budget 2026-27 announced seven more high-speed corridors of nearly 4,000 km, with investment of about ₹16 lakh crore.
High-speed rail 'growth connectors' announced in Union Budget 2026-27 (~4,000 km, ~₹16 lakh crore)
| Corridor | Projected travel time |
|---|---|
| Delhi-Varanasi | 3 h 50 min |
| Varanasi-Patna-Siliguri | 2 h 55 min |
| Chennai-Bengaluru | 1 h 13 min |
| Bengaluru-Hyderabad | 2 h |
| Chennai-Hyderabad | 2 h 55 min |
| Mumbai-Pune | 48 min |
| Pune-Hyderabad | 1 h 55 min |
| Aspect | Vande Bharat | MAHSR bullet train |
|---|---|---|
| Class | Semi-high-speed | High-speed (>250 kmph) |
| Design speed | 180 kmph | 350 kmph |
| Track | Existing Indian Railways network | Dedicated standard-gauge corridor, J-Slab ballastless |
| Origin | Indigenous, built by ICF Chennai; first run New Delhi-Varanasi, 15 Feb 2019 | Japanese Shinkansen (Tokaido line opened 1 Oct 1964) |
Joint-venture SPV to finance, build and run HSR corridors; under the Ministry of Railways
Japan's official development assistance agency; lends the soft ODA loan for MAHSR
GS Paper 3 > Infrastructure > Railways
General Awareness > Indian Railways
Shinkansen-type ballastless slab track, laid for the first time in India on MAHSR.
Launching an entire pre-cast viaduct span at once instead of segment by segment; first use in India.
New Austrian Tunnelling Method: support adjusted in real time to the rock met during excavation.