Tarapur Atomic Power Station (TAPS) Units 1 and 2 in Maharashtra, commissioned in 1969, are the world's oldest operating commercial nuclear reactors. The Atomic Energy Regulatory Board (AERB) has approved them to operate for about 10 more years.
Units 1 and 2 have generated more than 100 billion units of electricity and avoided over 86 million tonnes of CO2-equivalent emissions. On 17 June 2026 the DAE Secretary and AEC Chairman, Dr. Ajit Kumar Mohanty, reviewed the life extension at the site and inaugurated a Primary Coolant Pump Test Facility.
TAPS 1 and 2 are 160 MWe boiling water reactors built by General Electric under a 1963 India-US agreement. They were India's first nuclear power station and the first in Asia outside the Soviet bloc.
Nuclear safety regulator. It was constituted on 15 November 1983 by the President under Section 27 of the Atomic Energy Act, 1962, and it granted the TAPS 1 and 2 life extension.
Public sector company that builds and operates India's nuclear power plants, including TAPS. It was registered in September 1987 under the Companies Act, 1956.
Apex policy body for atomic energy. It was first set up in August 1948 and re-established within DAE by a resolution of 1 March 1958. The DAE Secretary is its ex-officio Chairman.
Set up on 3 August 1954 under the direct charge of the Prime Minister
| Aspect | TAPS 1 & 2 | TAPS 3 & 4 |
|---|---|---|
| Type | Boiling Water Reactor (BWR) | Pressurised Heavy Water Reactor (PHWR) |
| Capacity | 160 MWe each | 540 MWe each |
| Commissioned | 1969 | 2005-06 |
| Fuel / moderator | Enriched uranium; ordinary (light) water | Natural uranium; heavy water |
| Design origin | Imported: General Electric, USA | Indigenous; India's first units above 500 MWe |
In a BWR, ordinary water cools the core and boils inside the reactor vessel. The steam it produces drives the turbine directly, with no separate steam generator. That design needs enriched uranium, whereas India's indigenous PHWRs run on natural uranium moderated by heavy water.
GS Paper 3 > Science & Technology > Nuclear Energy
General Awareness > Science & Technology / Power Plants
Regulatory permission to run a reactor beyond its earlier licensed life, granted after refurbishment and safety review
The water that carries heat away from the reactor core. The new PCPTF tests the pumps that circulate it.
A contract under which a supplier builds the whole plant and hands it over ready to run. GE built TAPS 1 and 2 this way.