On 3 July 2026, Gujarat revised compensation for farmland used by power transmission towers and lines. Tower-base land will be paid at twice the prevailing market value, replacing 200% of the jantri (government circle rate).
A district Market Rate Committee will fix market value. It includes the Collector, landowner and farmer representatives, a market valuer and the transmission company.
Right of Way corridor compensation will be 30% of market value in rural areas, 45% in municipal areas and 60% in municipal corporation areas.
The whole amount will be paid upfront, before work begins, instead of the old 40-40-20 instalments. Projects still under execution are covered too.
Lets the appropriate government give a transmission licensee the powers a telegraph authority has to place lines on private land. Lines are laid with compensation for damage; the land is not acquired, which is why Gujarat revised compensation rates rather than acquisition rules.
District body that fixes market value for compensation
GS Paper III > Infrastructure - Energy; Land Reforms
General Awareness > States
Gujarat's official circle rate for land and property
The land corridor beneath an overhead transmission line