On the night of 19 September 2026, water gushed out of ADIT-V of the head race tunnel of NHPC's 800 MW Parbati-II hydroelectric project in Kullu, Himachal Pradesh, flooding Palchara village in Raila panchayat of the Sainj Valley.
The water carried debris from an NHPC dumping site into homes: about 15 families were hit, three houses buried and shops, a homestay, orchards and fields damaged.
An FIR was registered against the project's management on 21 September, and a 12-member inquiry committee headed by the Sainj Tehsildar was told to report within five days.
Parbati-II, a run-of-the-river project on the Parbati (a Beas tributary), has India's longest hydro head race tunnel (31.56 km) and has been fully commercial since 16 April 2025.
First three 200 MW units declared commercially operational
Fourth unit commercial - full 800 MW running
Water and muck burst out of ADIT-V into Palchara village
FIR registered against NHPC project management; 12-member inquiry committee formed
Builds and owns Parbati-II; India's largest hydropower company
The Parbati rises in the Kullu Himalaya and joins the Beas. Parbati-II dams it near Pulga in the Manikaran valley and carries the water through the mountain to a powerhouse at Siund in the neighbouring Sainj Valley, picking up flow from five nalas on the way. The flooded village, Palchara, lies in the Sainj Valley.
GS Paper I > Himalayan rivers; GS Paper III > Infrastructure - energy; Disaster management
General Awareness > Dams and power projects
Consider the following States: 1. Andhra Pradesh 2. Kerala 3. Himachal Pradesh 4. Tripura How many of the above are generally known as tea-producing States?
Answer: All four States
Which state has the maximum percentage of working female population as per Census 2011?
Answer: Himachal Pradesh
Diverts river flow through a tunnel to a turbine with little or no storage reservoir
Tunnel carrying water from the intake to the surge shaft and penstocks
A side access tunnel driven into the main tunnel during construction