The Taroki-Rowghat section (17.5 km), the last stretch of the 95 km Dallirajhara-Rowghat new line in Chhattisgarh, has been completed. The CRS inspection and speed trial were done on 22 September 2026.
The line will carry iron ore from SAIL's Rowghat mines to the Bhilai Steel Plant.
It is Phase I of a planned 235 km Dallirajhara-Jagdalpur line. Phase II is the 140 km Rowghat-Jagdalpur stretch.
General Awareness > Indian Railways and Industries
A statutory safety check by the Commission of Railway Safety that must be passed before a new line can open