The Northeast Frontier Railway said on 23 September 2026 that piling for the second Saraighat rail-cum-road bridge over the Brahmaputra at Guwahati will begin in October 2026. Larsen & Toubro is building it.
The 1.3-km double-decker bridge will carry two railway lines on its lower deck and a three-lane road with a footpath on its upper deck.
It is part of the 7.2-km Agthori–Kamakhya rail doubling sanctioned in 2024. The bridge was sanctioned in 2023-24 at about Rs 1,473.77 crore and is targeted for completion by December 2029.
The original Saraighat Bridge was the first rail-cum-road bridge across the Brahmaputra in Assam; its first engine crossed on 23 September 1962.
First engine crosses the original Saraighat Bridge
PM Jawaharlal Nehru dedicates the bridge, named after the Battle of Saraighat
Second rail-cum-road bridge sanctioned
Agthori–Kamakhya doubling sanctioned
Piling works to begin
Targeted completion
Railway zone executing the project; one of Indian Railways' zones
Apex body of Indian Railways that approves and monitors the project
Agthori lies on the north bank of the Brahmaputra and Kamakhya on the south bank, in Guwahati. The Saraighat crossing is the main rail link between the Northeast and the rest of India. The Brahmaputra rises in Tibet as the Yarlung Tsangpo, enters Arunachal Pradesh as the Siang/Dihang, and flows into Bangladesh as the Jamuna.
GS Paper 3 > Infrastructure – Railways; GS Paper 1 > Rivers of India
General Awareness > Railway zones and projects
Steel truss girder with open triangulated webs, used for long rail spans
Deep caisson foundation sunk into a riverbed; standard for large alluvial rivers
Adding a second line so that trains can run both ways at once