The Union Cabinet approved Green Energy Corridor Phase-III (GEC-III) on 30 September 2026 to strengthen intra-state transmission for evacuating up to 135 GW of renewable energy.
GEC-III also funds 50 GWh of Battery Energy Storage Systems; total outlay is Rs 1,86,405 crore with Central Financial Support of Rs 54,082 crore, to be set up by FY 2032-33.
Greenfield lines will be bid out under Tariff Based Competitive Bidding (BOOM model); State Transmission Utilities are the implementing agencies.
The scheme is linked to India's target of 900 GW installed non-fossil capacity by 2035.
| Aspect | GEC Phase-I | GEC Phase-II | GEC Phase-III |
|---|---|---|---|
| Launched/approved | 2015-16 | CCEA, 6 January 2022 | Cabinet, 30 September 2026 |
| RE to be evacuated | ~24 GW | ~20 GW | Up to 135 GW + 50 GWh BESS |
| Network | ~9,700 ckm lines, 22,600 MVA substations | 10,750 ckm lines, 27,500 MVA substations | Not specified in release |
| States | 8: TN, Karnataka, Rajasthan, AP, Maharashtra, Gujarat, HP, MP | 7: Gujarat, HP, Karnataka, Kerala, Rajasthan, TN, UP | All States/UTs |
| Cost | Rs 10,141.68 crore | Rs 12,031.33 crore | Rs 1,86,405 crore |
| Funding | 40% MNRE grant, 40% KfW (Germany) loan, 20% STU equity | 33% central assistance (Rs 3,970.34 crore) | Rs 54,082 crore central support |
| Timeline | - | 2021-22 to 2025-26 | By FY 2032-33 |
Evacuate about 13 GW of renewable power from Ladakh
Key: Separate inter-state (ISTS) project of about Rs 20,800 crore, distinct from the intra-state GEC phases
Make battery storage bankable
Key: Approved September 2023: Rs 3,760 crore for 4,000 MWh, VGF up to 40% of capital cost
30 GWh of BESS across 15 States and NTPC
Key: Rs 5,400 crore from the Power System Development Fund (PSDF); Rs 18 lakh/MWh; 25 GWh to States, 5 GWh to NTPC
India's five climate pledges
Key: Includes 500 GW non-fossil capacity by 2030; the 50% non-fossil share of installed capacity was reached in June 2025, five years early
Solar peaks at midday and vanishes at night, so lines congest at noon and RE is curtailed. Batteries store surplus generation and release it in non-solar hours, easing congestion and evening peaks without building extra lines.
Simple Analogy: A water tank that fills at noon and supplies the evening rush.
Provides for the State Transmission Utility, which plans and builds the intra-state network; STUs implement GEC-III
Tariff discovered through transparent competitive bidding is adopted by the regulator — the basis of TBCB for greenfield GEC-III lines
Used for brownfield upgradation and network strengthening, where the regulator allows cost plus a return
GS Paper 3 > Infrastructure: Energy; Environment > Renewable Energy
General Awareness > Government Schemes
General Awareness > Economy > Infrastructure Financing
Read the below statements marked as Assertion (A) and Reason (R). Mark the correct options: Assertion (A): UDAN Scheme improves regional air connectivity. Reason (R): It provides financial viability gap funding to airlines.
Answer: Both A and R are true, and R is the correct explanation of A
Intra-State Transmission System — the state grid built by the State Transmission Utility, as against the inter-state ISTS.
Tariff Based Competitive Bidding — the bidder quoting the lowest transmission tariff wins; tariff adopted under Section 63.
Build-Own-Operate-Maintain — the private TSP keeps ownership and runs the asset.
Forced reduction of renewable output because the grid cannot absorb or carry it.