On 14 October 2026, local farmers gave up about 70 acres inside the Full Tank Level (FTL) of Kapra Lake, north-east Hyderabad, for its restoration, handing consent letters to HYDRAA Commissioner A.V. Ranganath
The lake's FTL area is 112.80 acres. HYDRAA's roughly Rs 35 crore project is about 60% complete, and Kapra is one of 14 lakes in the agency's second phase
The works include desilting, deepening and upgraded inlets and outlets, aimed at flood mitigation, groundwater recharge and habitat for more than 470 migratory bird species
HYDRAA was created by Telangana's GO 99 in July 2024 and given statutory powers in October 2024 through Section 374-B of the GHMC Act, 1955
Protects lakes, parks and other public assets from encroachment, and handles disaster response in the Telangana Core Urban Region up to the Outer Ring Road, which covers GHMC and parts of Hyderabad, Rangareddy, Medchal-Malkajgiri and Sangareddy districts
Telangana order that created HYDRAA and defined its area, the Telangana Core Urban Region up to the ORR
Promulgated in October 2024 after HYDRAA's powers were challenged in court. It lets a designated agency use the corporation's and Commissioner's powers to protect public assets, which put HYDRAA on a statutory footing
The FTL is the boundary water reaches when a lake is at its highest designed storage level. The buffer zone is a strip of land running parallel to and outside the FTL where construction is restricted. Encroachment into either one shrinks flood storage and recharge.
Simple Analogy: FTL is the bathtub's rim; the buffer is the dry mat around it.
General Awareness > State news (Telangana) > Environment
The boundary of a lake at its highest designed water level, used to mark lake land against encroachment
Hyderabad Disaster Response and Asset Protection Agency, set up in July 2024