Central Electricity Authority (CEA) data showed 96 of India's 191 coal-fired power plants holding critically low stocks - under three days of fuel - as of 19 October 2026, up from 60 in mid-September.
Total coal stocks at power stations fell about 5% since the start of October, even as daily coal supply to the power sector rose about 36% over September levels.
Daily peak demand in 2026 has run 45-50 GW above 2025; September's demand-supply gap of 560 million kWh was the widest since August 2023.
El Nino-linked heat raised demand while a weak monsoon cut September hydropower output by 20%, pushing coal generation up 13.3% year-on-year.
The government put a proposal to make plants import coal on hold - high global prices and a weaker rupee - and asked Coal India to raise output and the railways to speed deliveries.
Statutory body under the Electricity Act, 2003 (Section 70); technical adviser to the Ministry of Power; publishes daily coal-stock reports for power plants
State-owned coal miner, the bulk of India's domestic coal output; asked to raise production
Coordinates supply to power plants with CIL and the railways; says 'critical' is a warning tag, not an outage
El Nino is the periodic warming of sea-surface waters in the central and eastern tropical Pacific. It usually weakens India's southwest monsoon and brings heat - demand for cooling rises while reservoirs fill less, so hydropower falls and coal plants carry the extra load.
Simple Analogy: Two taps feed one bucket; when one runs dry, the other must run harder.
GS Paper III > Infrastructure: Energy; GS Paper I > Climate (El Nino-monsoon link)
General Awareness > Economy / Energy
With reference to 'Indian Ocean Dipole (IOD)' sometimes mentioned in the news while forecasting Indian monsoon, which of the following statements is/are correct? 1. IOD phenomenon is characterised by a difference in sea surface temperature between tropical Western Indian Ocean and tropical Eastern Pacific Ocean. 2. An IOD phenomenon can influence an El Nino's impact on the monsoon. Select the correct answer using the code given below:
Answer: 2 only
Fuel at a plant enough for fewer than three days of generation, as reported in the CEA data cited
Highest electricity demand met at any moment, measured in gigawatts (power), unlike kWh which measures energy
Warm phase of ENSO in the central-eastern tropical Pacific; usually linked to a weaker Indian monsoon