Saidongar-1, a 3,000 MW pumped storage project in Karjat taluka of Raigad district, Maharashtra, will be India's largest pumped storage plant; it is being built by a subsidiary of Torrent Power.
Tree felling for the project drew protests from 24 to 26 October 2026. The Forest Department reportedly permitted the felling of 32,490 trees, and the project needs 233 ha of forest land.
Shiv Sena (UBT), NCP (SP), Congress and MNS oppose the felling. CM Devendra Fadnavis says due process was followed, with hearings held over 18 months.
The project lies about 15.5 km from Bhimashankar Wildlife Sanctuary and outside its eco-sensitive zone, so it needs no wildlife clearance. The MoEFCC's Expert Appraisal Committee recommended environmental clearance on 13 October 2025.
MoEFCC issues the first Terms of Reference (ToR), for a closed-loop design
Torrent PSH 3 signs an MoU with Maharashtra's Water Resources Department for the 3,000 MW project
Online proposal filed to divert 233 ha of forest land
Central Electricity Authority (CEA) approval
Fresh ToR issued after the design changed to open loop
Maharashtra's Revenue & Forest Department sends the MoEFCC its recommendation to divert the 233 ha
41st meeting of the EAC (River Valley & Hydroelectric Projects) recommends environmental clearance
L&T wins the civil and hydro-mechanical works contract
ANDRITZ wins the electromechanical equipment order
NCP (SP) MLA Rohit Pawar alleges felling of 32,000+ trees; the Pune Forest Department denies any felling inside Bhimashankar WLS
CM Devendra Fadnavis defends the project and calls the opposition's case a 'fake narrative'
Aaditya Thackeray visits the Saidongar site; MoS Energy Meghna Bordikar accuses the opposition of 'selective opposition'
Forest land can be diverted to a non-forest use only with the Central Government's prior approval. This is why the 233 ha diversion went from the State to the MoEFCC for forest clearance
Hydroelectric projects are listed under item 1(c) of its Schedule. As a Category 'A' project, Saidongar-1 is appraised by the central Expert Appraisal Committee and cleared by the MoEFCC, after a public hearing
Bhimashankar is a wildlife sanctuary under this Act. The project lies outside the sanctuary's eco-sensitive zone, so no separate wildlife clearance was required
A developer that diverts forest land pays for compensatory afforestation through CAMPA; the draft EIA includes a compensatory afforestation plan
Grants environmental clearance and forest clearance (forest land diversion) for Category A projects
Expert panel set up under the EIA Notification, 2006. Appraised Saidongar-1 and recommended clearance at its 41st meeting (13 October 2025)
Statutory technical adviser under Section 70 of the Electricity Act, 2003. Concurs hydro and pumped storage project plans and tracks pumped storage development
Parent company of the developer, Torrent Energy Storage Solutions (formerly Torrent PSH 3)
The project sits on the Sahyadri (Western Ghats) slopes of Karjat taluka in Raigad district. Its lower reservoir crosses the Pej river. Bhimashankar Wildlife Sanctuary lies about 15.5 km away on the crest of the Ghats. Notified in 1985 over about 131 sq km in Pune, Thane and Raigad districts, it protects the Indian giant squirrel (shekru, Ratufa indica elphinstonii), Maharashtra's state animal.
GS Paper 3 > Environment: EIA and forest clearance; Infrastructure: Energy storage
General Awareness > Current Affairs: India's largest projects
From the ecological point of view, which one of the following assumes importance in being a good link between the Eastern Ghats and the Western Ghats?
Answer: Sathyamangalam Tiger Reserve
In which of the following regions of India are you most likely to come across the 'Great Indian Hornbill' in its natural habitat?
Answer: Western Ghats
'Gadgil Committee Report' and 'Kasturirangan Committee Report', sometimes seen in the news, are related to
Answer: protection of Western Ghats
Consider the following statements: 1. In India, the Himalayas are spread over five States only. 2. Western Ghats are spread over five States only. 3. Pulicat Lake is spread over two States only. Which of the statements given above is/are correct?
Answer: 3 only
The "Western Ghats" are also known as:
Answer: Sahyadris
A 'water battery': surplus power pumps water uphill, and it is released through turbines when demand peaks
A PSP with at least one reservoir on a natural river. A closed-loop PSP has no link to any natural water body
The Central Government's prior approval, under the Van (Sanrakshan Evam Samvardhan) Adhiniyam, 1980, to use forest land for a non-forest purpose