NTPC Ltd terminated a Rs 413.37 crore contract awarded to GR Infraprojects Ltd for a 400 MWh Battery Energy Storage System at its Mouda Super Thermal Power Station in Maharashtra, disclosed on 19 September 2026.
The contract had been awarded in March 2026 with a completion period of 15 months, but critical activities fell behind and the contractor did not act on a contractual notice to correct course.
NTPC encashed securities worth about Rs 91 crore under the contract's provisions and said its focus would now be on re-awarding the project and getting it built on time.
The project is meant to add grid flexibility and help absorb renewable generation, which is why the delay matters beyond the single site.
India's projected requirement is far larger: the National Electricity Plan works with about 236 GWh of battery storage by 2031-32 out of roughly 411 GWh of total energy storage, the rest coming from pumped hydro.
A BESS is more than cells. It needs a Battery Management System watching cell voltage, temperature and state of charge; a Power Conversion System that turns stored DC into usable AC and back while charging; thermal management; a control system that decides when to charge or discharge; and an enclosure. It is rated twice over - in kWh for how much it stores and kW for how fast it can deliver.
Simple Analogy: A water tank: its size is one number, the width of its outlet pipe is another.
Bring down the cost of storage-backed power so discoms will contract it
Key: Central support has been approved for about 43.8 GWh of BESS capacity, broadly covering the nearer-term requirement rather than the 2031-32 need
Improve project economics for storage built alongside renewable generation
Key: A 100 per cent waiver of ISTS charges for eligible co-located battery and pumped storage projects
Size India's storage requirement against rising renewable capacity
Key: Projects a need for roughly 411 GWh of energy storage by 2031-32 - about 236 GWh from batteries and about 175 GWh from pumped hydro
Maharatna central public sector power generator that awarded and then terminated the contract; set up in 1975
Prepares the National Electricity Plan, whose projections set India's energy storage requirement
Administers the storage policy framework, including viability gap funding and transmission charge waivers
GS Paper 3 > Infrastructure: energy, and renewable energy integration
General Awareness > PSUs, large contracts and the power sector
Recently, term the "pumped-storage hydropower" is actually and appropriately discussed in the context of which one of the following?
Answer: Long duration energy storage
A system storing electricity in rechargeable batteries and releasing it on demand, rated in kWh for energy and kW for power
Discharging stored energy at times of highest demand so that costly peaking generation or higher tariffs are avoided
Capital support from the government that closes the gap between a project's cost and what buyers will pay, used here to make storage-backed power affordable