The Union Cabinet approved a Viability Gap Funding (VGF) Scheme for Grid-Scale Energy Storage Systems with Rs 14,500 crore of support for FY 2026-27 to FY 2030-31.
It targets 92 GWh of new storage — 60 GWh hydro pumped storage, 30 GWh battery storage (BESS) and 2 GWh of alternative technologies — with total investment estimated at Rs 97,600 crore.
BESS projects must meet a minimum 40% Domestic Content Requirement; capacity will be allocated through tariff-based competitive bidding.
The new capacity equals 170% of today's grid-scale storage and goes towards the 411 GWh of grid-scale storage India needs by 2031-32.
It follows two earlier BESS-only VGF schemes: Rs 3,760 crore (September 2023) and Rs 5,400 crore from the Power System Development Fund (June 2025).
A one-time capital grant that covers the gap between a project's cost and what it can earn, so a socially needed but commercially unviable project can attract bidders. Bidders compete on tariff, so the subsidy lowers the price the discom pays.
Kick-start standalone battery storage
Key: Rs 3,760 crore; up to 40% of capital cost; original target 4,000 MWh, later scaled up as battery prices fell
Scale batteries further
Key: Rs 5,400 crore from the Power System Development Fund for 30 GWh; Rs 18 lakh per MWh
Supply-side support for domestic cell manufacturing
Key: Rs 18,100 crore for 50 GWh of ACC capacity plus 5 GWh of niche cells; run by the Ministry of Heavy Industries. The new scheme's DCR is the demand-side complement.
Create demand for stored renewable power
Key: Share of energy from solar/wind with storage rises from 1% in 2023-24 to 4% by 2029-30
Faster pumped storage build-out
Key: Guidelines of 10 April 2023; 100% ISTS charge waiver for 25 years for PSPs whose construction is awarded by 30 June 2028
Capacity goal storage must balance
Key: 500 GW of non-fossil capacity by 2030; capacity stood at 310 GW in November 2026 (MNRE)
| Aspect | BESS | Pumped storage |
|---|---|---|
| Share of this scheme | 30 GWh | 60 GWh |
| How it stores | Chemical energy in cells | Water pumped uphill, released through turbines at peak |
| Domestic content rule | Minimum 40% DCR | Not specified in the release |
| India's status | Two earlier VGF rounds | 7.43 GW operational across 10 projects (August 2026); 15.87 GW under construction |
| Biggest example | — | Pinnapuram, Andhra Pradesh (1,680 MW), off-stream closed loop |
Statutory technical adviser to the Ministry of Power; prepares the National Electricity Plan and storage requirement estimates. Originally constituted under the Electricity (Supply) Act, 1948; now under Section 70 of the Electricity Act, 2003; up to 14 members
Fund created under CERC regulations (2010), operationalised by the Ministry of Power in 2014; fed by congestion, deviation-settlement and reactive energy charges; financed the 2025 BESS VGF
GS Paper 3 > Infrastructure > Energy; Environment > Renewable Energy
General Awareness > Government Schemes
General Awareness > Current Affairs > Schemes
The term 'Domestic Content Requirement' is sometimes seen in the news with reference to
Answer: Developing solar power production in our country
Read the below statements marked as Assertion (A) and Reason (R). Mark the correct options: Assertion (A): UDAN Scheme improves regional air connectivity. Reason (R): It provides financial viability gap funding to airlines.
Answer: Both A and R are true, and R is the correct explanation of A
Who was the Minister of Science and Technology (as of 2024 question context)?
Answer: Dr. Jitendra Singh
Recently, term the "pumped-storage hydropower" is actually and appropriately discussed in the context of which one of the following?
Answer: Long duration energy storage
A minimum share of a project's value that must be made in India; 40% for BESS under this scheme.
Capacity goes to the bidder offering the lowest tariff, so the subsidy shows up as a cheaper price.
GW is power (rate of delivery); GWh is energy (how much can be stored and released).
A closed-loop scheme with reservoirs not on a flowing river; most of India's mapped potential is of this type.