NHAI has issued guidelines making median and avenue plantation an integral component of national highway development and project completion.
A Provisional Certificate of Completion (PCC) or Provisional Commercial Operation Date (PCOD) will be issued only if plantation covers at least 80% of the Right of Way earmarked for it, with a minimum 90% sapling survival rate at inspection.
The 90% survival rate must be maintained through the Operations and Maintenance period: O&M and annuity payments in EPC, HAM and BOT-Annuity projects, and maintenance compliance in BOT-Toll projects, are made conditional on it, with financial withholdings for shortfalls.
GS Paper 3 > Infrastructure > Roads; Environment > Afforestation
NHAI's certification that a highway project is substantially complete and may open to traffic, now conditional on plantation compliance.
A highway contracting model blending EPC and BOT, where the government funds part of the cost during construction and pays the rest as annuities during operations.