The Expert Appraisal Committee for River Valley and Hydroelectric Projects has recommended environmental clearance for SJVN Limited's 680 MW Attunli Hydroelectric Project in the Dibang Valley district of Arunachal Pradesh.
Attunli is a run-of-river project built around an 85-metre concrete gravity dam on the Tangon, also called the Talo, river.
Its underground powerhouse will hold four Francis turbines of 170 MW each and the project is expected to generate about 2,728 million units a year.
The project needs the diversion of 261.53 hectares of forest land, for which Stage-I forest clearance was granted in June 2026.
Originally conceived by a joint venture of Jindal Power and the Hydro Power Development Corporation of Arunachal Pradesh, the project was later allotted to SJVN.
Under the Environment Impact Assessment Notification of 2006, a project of this category is appraised by an Expert Appraisal Committee constituted by the Ministry of Environment, Forest and Climate Change. The committee examines the environmental impact assessment and management plan and then recommends grant or refusal; the actual environmental clearance is issued by the regulatory authority, not by the committee itself. Running in parallel and quite separately, any diversion of forest land requires approval under the forest conservation law, which comes in two stages: Stage-I, an in-principle approval carrying conditions, and Stage-II, the final approval once those conditions are met. A project can hold Stage-I forest clearance and a favourable environmental appraisal and still not be free to start work.
Simple Analogy: The appraisal committee is the examiner who recommends a pass; the certificate is issued by someone else, and the forest department runs a completely separate examination.
Central public sector hydropower developer, a joint venture of the Government of India and the Government of Himachal Pradesh; its first and flagship project is the 1,500 MW Nathpa Jhakri plant on the Sutlej
Constituted under the Environment Impact Assessment Notification, 2006, to appraise river valley and hydroelectric proposals and recommend grant or refusal of environmental clearance
GS Paper 3 > Infrastructure: energy; Environmental impact assessment; Conservation
General Awareness > Indian Economy and Current Affairs
Consider the following rivers: 1. Barak 2. Lohit 3. Subansiri Which of the above flows/flow through Arunachal Pradesh?
Answer: 2 and 3 only
Which one of the following pairs of States of India indicates the easternmost and westernmost State?
Answer: Arunachal Pradesh and Gujarat
Which one of the following National Parks has a climate that varies from tropical to subtropical, temperate and arctic?
Answer: Namdapha National Park
Consider the following States: 1. Arunachal Pradesh 2. Himachal Pradesh 3. Mizoram In which of the above States do 'Tropical Wet Evergreen Forests' occur?
Answer: 1 and 3 only
In which one of the following States is Pakhui Wildlife Sanctuary located?
Answer: Arunachal Pradesh
A hydroelectric plant that generates from the natural flow of a river with limited storage, as distinct from a storage or reservoir scheme
The tunnel carrying water from the intake to the powerhouse, creating the head that drives the turbines
A vertical shaft that absorbs sudden pressure changes in the water conductor system when the turbine load changes, protecting the tunnel
A reaction turbine suited to medium heads and the most widely used type in Indian hydropower stations
In-principle approval for diversion of forest land, carrying conditions that must be met before final Stage-II clearance is issued